Share
East Bank bypass road project redesigned to fit US$50M loan

East Bank bypass road project redesigned to fit US$50M loan

GOVERNMENT has retailored the Ogle to Diamond bypass road project to conform with the loan available to execute the major works.
Speaking with the Department of Public Information, Minister within the Ministry of Public Works, Deodat Indar, said the new four-lane East Coast-East Bank Linkage Project will extend from Ogle to Haags Bosch, rather than to Diamond.
This move will spare taxpayers approximately USD$158M.

“What was driving up that [project] cost was a number of connectors on the road,” Minister Indar cited.
Identifying the previously proposed connection at Mocha as a difficult area to execute works, the minister noted the swamp terrain saw astronomical increases in the total project cost.

Project Design of the East Coast-East Bank Linkage Project
Project Design of the East Coast-East Bank Linkage Project

“For you to do those swamps, the cost of the earth works pushed up the cost to $208M. Remember, the Indian Government only had $50M allocated to this project. So, we had to redesign the project to bring it to the original design,” Minister Indar explained.

The minister further confirmed that India has accepted the new design for the roadworks. As such, the government is moving ahead to implement the project that was stalled for five years under the former APNU+AFC coalition administration.

At the completion of Phase one of the project (Diamond to Hague Bosch), Minister Indar said the administration will forge ahead with the extension of the bypass road further up the East Bank of Demerara to Timehri.

Leave a Comment